How to cure open violations before you buy a building

How to cure open violations before you buy a building

How to cure open violations before you buy a building

How buyers of New York buildings find, cure and clear open DOB, OATH and HPD violations before closing, and what to do when time runs out.

7 min read

New York multifamily building facades with exterior fire escapes

SHARE

KEY TAKEAWAYS

  • Violations stay with the property. A buyer who closes without a plan inherits the conditions, the penalties and the paperwork.

  • Fixing the condition is only half the job. Each agency has its own filing to prove the fix, and the violation stays open on the public record until that filing is accepted.

  • Timing decides the deal. Some violations can be cleared in days; others need permits, inspections or hearings. Know which is which before you sign.

Why violations belong in due diligence

For many buyers, violations show up late: in a title report, a lender’s checklist or a broker’s last-minute note. By then the choices are narrow. Close and inherit the problem, delay the closing, or renegotiate under pressure.

Buyers who treat violations as a construction question rather than a paperwork question do better. The real questions are what condition caused each violation, what it will take to correct, who must approve the correction, and how long that approval takes.

Three agencies, three different processes

Most open violations on a New York building come from three sources.

The Department of Buildings. DOB issues violations and summonses for unsafe conditions, work without permits and failures to file required inspections. Immediately hazardous conditions must be corrected right away, and the correction is proved by filing a Certificate of Correction through DOB NOW: Safety.

OATH summonses. Many building summonses are heard by the Office of Administrative Trials and Hearings. An OATH violation stays active on the property’s public profile until it is dismissed at a hearing or resolved through Certificate of Correction review. Work without a permit carries an added DOB civil penalty that must be paid, or waived, before the certificate will be approved.

HPD. The Department of Housing Preservation and Development issues housing maintenance violations in residential buildings, in three classes with different correction periods.

Class A: Non-hazardous. 90 days from receipt of the notice.

Class B: Hazardous. 30 days from receipt of the notice.

Class C: Immediately hazardous. 24 hours in most cases (21 days for lead and window guard violations).

An owner who corrects an HPD violation within its period can certify the correction online at no cost. Violations past their certification period need a dismissal request, which requires an HPD inspection and a fee of $250 to $1,000 depending on the building and the number of open violations. HPD aims to inspect within 45 days in summer and 90 days in winter, so late violations can take months to clear.

The path to a clean record

Exhibit 1. A violation clears when the agency accepts the proof, not when the work ends

Exhibit 1. A violation clears when the agency accepts the proof, not when the work ends

When the agency cannot accept the proof before the closing date, the remaining work becomes a pricing question rather than a reason to walk away.

Fixing the condition is only half the job. The violation stays open until the agency accepts the proof.

Five steps before you sign

  1. Pull every record. Search the building on DOB’s public systems, OATH’s summons records and HPD Online. Note each violation’s agency, class, date and penalty.

  2. Walk the building with the list. Match each violation to a real condition. Some are already fixed and only need paperwork; others hide larger problems.

  3. Sort by time to clear. Separate paperwork-only items, quick physical fixes, and items that need permits, licensed trades, inspections or hearings.

  4. Price what cannot clear in time. For items that will outlast the closing date, work with counsel on an escrow, a price credit or a seller covenant to finish the work.

  5. Assign one team to finish the job. Corrections, filings and follow-up across three agencies go faster under one construction and compliance lead than across several vendors.

This article is general guidance, not legal advice. Agency rules and fees change; confirm current requirements with each agency and your counsel.

Sources

  • NYC DOB: Certificate of Correction

  • NYC DOB: What is an OATH Summons?

  • NYC HPD: Clearing HPD Violations

Questions owners ask

Planning a project in New York City?

Talk to SRE

Construction management and engineering for New York’s infrastructure and buildings.

Construction management and engineering for New York’s infrastructure and buildings.

Construction management and engineering for New York’s infrastructure and buildings.

MBE · WBE CERTIFIED

MBE · WBE CERTIFIED

Manhattan

7 Park Avenue, 11th Floor
New York, NY 10016

© 2026 SRE Engineering, D.P.C.

·

Pushing New York Forward